APMG-International AgilePM-Foundation (Agile Project Management (AgilePM) Foundation) Exam provides professionals with the fundamental knowledge and practical skills required to manage projects in an agile environment. Agile Project Management (AgilePM) Foundation Exam certification process enhances employability prospects, enabling professionals to take up high-paying project management roles. Agile Project Management (AgilePM) Foundation Exam certification is recognized worldwide, adding value to individuals' resumes while boosting employers' productivity and expanding their reach. The AgilePM Foundation Exam is a crucial learning module for professionals seeking to develop their project management expertise and practical skills in the current business environment.
NEW QUESTION # 12
Which of the following is NOT an interest into which each DSDM role is grouped?
- A. Maintenance
- B. Solution/Technical
- C. Management
- D. Business
Answer: C
NEW QUESTION # 13
What DSDM Principles requires the transparency of all work being performed by the team?
- A. Principle 8-Demonstrate Control
- B. Principle 66-Develop iteratively
- C. Principle 1 - Build incrementally from Firm Foundations
- D. Principle 1- Focus on the Business Need
Answer: A
NEW QUESTION # 14
Which technique allows for testing the achievailability of objectives?
- A. Modeling
- B. MoSCoW
- C. Timeboxing
- D. Facilitated Workshop
Answer: D
NEW QUESTION # 15
Which purpose relates to the instrumental Success Factors?
- A. Underpins the prioritization of requirements
- B. Inform the development of the Terms of Reference
- C. Informs the development of the Business Case
- D. Positions DSDM projects for a successful outcome
Answer: C
NEW QUESTION # 16
Which information is given in the Solution Architecture Definition?
- A. The tools and standards to be used in Evolutionary Development
- B. The strategy for testing
- C. A high-level design framework for the solution.
- D. A snapshot of the evolving business, solution and management products
Answer: D
NEW QUESTION # 17
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?
- A. Technical Coordinator
- B. Business Analyst
- C. Team Leader
- D. Business Visionary
Answer: D
NEW QUESTION # 18
What role is responsible for the delivery of the project from Foundations through to Deployment?
- A. Technical Coordinator
- B. Business Visionary
- C. Project manager
- D. Business Sponsor
Answer: C
NEW QUESTION # 19
What is the MoSCoW technical used for?
- A. Ensuring a team-based approach through visual and verbal communication and collaboration.
- B. Understanding and managing priorities.
- C. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
- D. Creating a visual representation of a problem or a solution.
Answer: B
NEW QUESTION # 20
During what DSDM phase is it established how quality to be assured?
- A. During Feasibility
- B. At the start of Evolutionary Development
- C. During each timebox during Evolutionary Development
- D. As part of Foundations
Answer: D
NEW QUESTION # 21
Which of the following is a DSMD principle?
- A. Build incrementally in Timeboxes
- B. Build incrementally
- C. Build incrementally from Feasibility onwards
- D. Build incrementally from firm foundations
Answer: D
NEW QUESTION # 22
Which responsibility relates to the role of the Business Ambassador?
- A. Provide day-to-day detail of the requirements during timeboxes
- B. Resolve business issues and make financial decisions
- C. Provide the team with strategic direction.
- D. Responsible for the Business Case and project budget.
Answer: D
NEW QUESTION # 23
How are the business roles critical to the success of a DSDM project?
- A. Make all decisions
- B. Provide formal progress reporting
- C. Guide the evolution of the solution at the detailed level
- D. Lead Solution Developer demonstrations
Answer: C
NEW QUESTION # 24
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
- A. Business Visionary
- B. Business Analyst
- C. Business Ambassador
- D. Workshop Facilitator
Answer: D
NEW QUESTION # 25
Which statement applies to the DSDM process?
- A. Can be configured and calibrated to cater for light or strong governance
- B. Does not require the elaboration of supporting products for complex projects
- C. DSDM projects can deliver the phases in the DSDM process in any order
- D. Provides an approach that can be used for all projects without change
Answer: A
NEW QUESTION # 26
During what phase should a baseline of the Evolving Solution be put into operational use?
- A. Post-Project
- B. Foundations
- C. Deployment
- D. Evolutionary Development
Answer: C
NEW QUESTION # 27
What does DSDM refer to the Minimum Usable Subset?
- A. The Must Have requirements
- B. Those requirements that have passed user acceptance testing
- C. All requirements in the functional specification
- D. The Must, Should and Could have requirements
Answer: A
NEW QUESTION # 28
In a free format Timebox, when should reviews take place?
- A. During the Close.Out phase
- B. After the Timebox has been completed
- C. Throughout the body of the Timebox.
- D. During the Kick-Off phase
Answer: C
NEW QUESTION # 29
Which of the following statements about the technical Coordinator role is true?
The technical Coordination provides the same function from a technical perspective as the Business Ambassador does from a business perspective.
The technical Coordinator is responsible for ensuring that the solution confirm to the requested technical standards.
- A. Neither 1 or 2 is true
- B. Only 2 is true
- C. Only 1 is true
- D. Both 1 and 2 are true
Answer: B
NEW QUESTION # 30
What phase will create Solution increments?
- A. Feasibility
- B. Deployment
- C. Foundations
- D. Evolutionary Development
Answer: D
NEW QUESTION # 31
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
- A. Management Approach Definition
- B. Delivery Plan
- C. Foundation Summary
- D. Terms of Reference
Answer: C
NEW QUESTION # 32
......
APMG-International AgilePM-Foundation Exam is an excellent certification for individuals who want to develop their skills in Agile project management. It is a globally recognized certification that is highly valued by employers and can enhance the candidate's career prospects. With the right preparation and dedication, candidates can pass the exam and become certified in Agile project management.